Questionable firms won Katrina contracts: Study

By Hope Yen
Associated Press Writer

WASHINGTON — FEMA exposed taxpayers to significant waste — and possibly violated federal law — by awarding $3.6 billion worth of Hurricane Katrina contracts to companies with poor credit histories and bad paperwork, investigators say.

The new report by the Homeland Security Department’s office of inspector general, set to be released later this week, examines the propriety of 36 trailer contracts designated for small and local businesses in the stricken Gulf Coast region following the 2005 storm.

It found a haphazard competitive bidding process in which the winning contract prices were both unreasonably low and high. Moreover, FEMA did not take adequate legal steps to ensure that companies were small and locally operated, resulting in a questionable contract award to a large firm with ties to the Republican Party.

‘Unacceptable level of risk’

“Based on our analysis, we concluded that FEMA contracting officials exposed the agency to an unacceptable level of risk,” according to the report by the office of inspector general Richard Skinner.

The audit was requested by Sen. Byron Dorgan, D-N.D., chairman of the Democratic Policy Committee, following complaints last year by some small business owners that they were unfairly shut out of the contracting process.

It is the latest to detail mismanagement in a multibillion-dollar hurricane recovery effort that investigators say has already wasted more than $1 billion.

Missed deadline

The report also comes after FEMA acknowledged earlier this month that it would not have a federal plan ready for responding to emergencies before the approaching hurricane season, which begins June 1.

In response, FEMA in the report disagreed that the wide price variations put taxpayers at risk. The agency contended that it was comfortable with bidders’ financial viability based in part on past performance. In cases where contract prices appeared unreasonably high, those would be offset with lower payments later on subsequent work orders, FEMA officials said.

In the immediate aftermath of Katrina, FEMA handed out lucrative no-bid contracts for cleanup work to large, politically connected firms such as Shaw Group Inc., Bechtel Group Inc., CH2M Hill Companies Ltd., and Fluor Corp.

Following heavy criticism, FEMA director David Paulison pledged to rebid those large contracts.

He ultimately reopened only a portion, awarding 36 contracts that the agency said would be prioritized for small and local businesses.

Prices also varied greatly. Some were so high that investigators deemed them unreasonably excessive and wasteful; others were so unreasonably low that taxpayers faced “an unacceptable risk of poor performance.”

For example, FEMA:

  • Accepted bids as low as $74 and as high as $4,720 to completely refurbish used travel trailers. FEMA estimated this service should cost $295 per trailer.

  • Accepted bids from companies with weak financial statements, incomplete and missing financial documentation, and negative net worth. The Defense Contract Audit Agency determined that at least three bidders presented high financial risks, but FEMA allowed the contracts to go forward.

    Copyright 2005 Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

    Save $84.50 a year off our newsstand price:
    Subscribe today for only 38 cents a day!

  • Leave feedback
    on this or
    another
    story.

    Email This Page


      www.decaturdaily.com